Railway Performance Society Magazine - Milepost

Huyton Energisation date.

Forum / News / Huyton Energisation date.

Reply         Subscribe         Start new thread         Syndicated Feed (RSS)        

Displaying 1 to 1 of 1 Previous   1   Next
Author Message
8001F

Posts: 5528
Location:
Huyton Energisation date. - Posted: September 9, 2017 - 11:21 PM Quote and reply
UP CHAT MOSS SLOW LINE BETWEEN ROBY JUNCTION AND HUYTON JUNCTION.
FROM 1200 HOURS SUNDAY 08 OCTOBER 2017 THE NEW OVERHEAD LINE EQUIPMENT BELOW WILL BE ENERGISED AT 25000 VOLTS, AND FROM THIS TIME MUST BE REGARDED AS BEING LIVE AT ALL TIMES
From the above date the new overhead line equipment on the Up Chat Moss Slow Line from structure number LM07/15 at Roby Jn to structure number LM09/16A at Huyton Jn will be energised.
NR 09.09.17

Back to top View user profile     Contact this member